ComponentOne GanttView for WinForms
Working with GanttView / Columns
In This Topic
    Columns
    In This Topic

    A grid comprises of rows and columns to record information. A column generally contains information of the same type, whereas a row can contain information of different data types.

    In GanttView, the collection of columns is represented by the ColumnCollection class which is accessible through the Columns property of the C1GanttView class.

    This section walks you through different operations that can be performed on columns in the GanttView control.

    Add Columns to Grid

    You can add a column to the ColumnCollection by using the Columns property of the C1GanttView class. To add columns to the grid, please refer to the code snippet provided below.

    C#
    Copy Code
    C1.Win.GanttView.TaskPropertyColumn taskPropertyColumn1 = new C1.Win.GanttView.TaskPropertyColumn();
    taskPropertyColumn1.Caption = "Duration";
    taskPropertyColumn1.ID = 1437604830;
    taskPropertyColumn1.Property = C1.Win.GanttView.TaskProperty.Duration;
    this.c1GanttView1.Columns.Add(taskPropertyColumn1);
    

    You can also add columns at run time. To add columns using the ColumnCollection of the GanttView, follow the steps below:

    1. Click the Grid Columns button,Displays Grid Columns icon in the GanttView. , to open the Grid Columns dialog box.
    2. Select the respective checkboxes to add new columns to the grid.
    3. Click OK.
      The two columns Duration and Start get added to the grid.

    Move Columns in Grid

    GanttView allows you to move columns to occupy new position in the grid.

    Shows how to move columns to occupy another position in the GanttView.

    To move the column at run time, follow the steps below:

    1. Select the column you wish to move.
    2. Drag the column and drop it to the target position.

    Custom Columns

    GanttView allows you to create custom columns as per your requirements. In GanttView, custom columns are represented by the CustomFieldColumn class. Other than this, you can also set various attributes of a custom column.

    Below code snippet shows how you can create a custom column in the GanttView control.

    C#
    Copy Code
    CustomFieldColumn cc = new CustomFieldColumn();
        cc.Caption = "My Numeric Column";
        cc.DataType = typeof(decimal);
        cc.Format = "$#0";
        cc.Name = "MyNumericColumn";
        cc.TextAlign = System.Windows.Forms.HorizontalAlignment.Right;
        cc.Width = 65;
        c1GanttView1.Columns.Add(cc);
    

    Dropdown in Custom Column

    A dropdown can be added to a custom column in the GanttView, as shown in the image below

    Dropdown in GanttView

    To add a dropdown in custom column, follow the steps below:

    1. Create an object of C1FlexGrid class and retrieve it as a child control of C1GanttView. This helps to access the custom column as an individual entity.
      C#
      Copy Code
      C1FlexGrid gridView = c1GanttView1.Controls[2] as C1FlexGrid;
      
    2. Add BeforeEdit event using the object of C1FlexGrid class as shown in the below code:
      C#
      Copy Code
      gridView.BeforeEdit += GridView_BeforeEdit;
      
    3. Create and add a ComboList to the custom column under the BeforeEdit event. The name passed for the grid column should match the caption of the custom column. In the following code, Task Priority is the caption of custom column and the values P1, P2, P3, and P4, are the values added to the combo list.
      C#
      Copy Code
      C1FlexGrid gridView = sender as C1FlexGrid;
      gridView.BeginUpdate();
      if (gridView.Cols[e.Col].Name == "Task Priority")
          gridView.Cols[e.Col].ComboList = "P1|P2|P3|P4";
      gridView.EndUpdate();
      

    Custom Multiple Rows and Columns

    Rows and columns in GanttView control can easily be customized. GanttView enables you to select multiple rows or columns and customize them according to your needs. You can indent and outdent the selected tasks, delete the tasks, and change their field styles. You can also select several cells to change field styles for the selected tasks/fields. Other than this, you can highlight a particular task by changing the font color and background style for that task name.

    To customize multiple rows and columns at the same time, follow the steps below:

    1. Select the rows/columns you want to customize.
    2. To change the height of the rows, place the cursor at the bottom of the selected row and drag it to adjust the height.
    3. To highlight a field, select Field Styles on the GanttView toolbar.
      Field Styles dialog box will appear.
    4. Select the field you want to customize from the drop down.
    5. Select the font style and background color that you want to apply.
    6. Click OK.
      The selected style and background color gets applied to the selected fields.

    Show Duration Columns in Grid

    Duration columns displays the total amount time taken to complete task. This is generally the length of time it takes to complete a task from beginning to end. You can show the duration columns in the grid by using the Duration and DurationUnits properties of the Task class.
    To programmatically show/hide the values of the Duration and DurationUnits properties in the grid, add the code given below:

    C#
    Copy Code
    private void chkShowDuration_CheckedChanged(object sender, EventArgs e)
    {
        TaskPropertyColumn durationCol = c1GanttView1.Columns.Search(TaskProperty.Duration);
        TaskPropertyColumn unitsCol = c1GanttView1.Columns.Search(TaskProperty.DurationUnits);
        if (durationCol != null && unitsCol != null)
        {
            bool visible = chkShowDuration.Checked;
            durationCol.Visible = visible;
            unitsCol.Visible = visible;
        }
    }